振冲置换法加固尾矿库坝的机理和应用
DOI:
作者:
作者单位:

作者简介:

通讯作者:

中图分类号:

TD824.71

基金项目:


Mechanism and Application of Vibration and Substitution Method in Reinforcement of Tailings Dam
Author:
Affiliation:

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
  • |
  • 文章评论
    摘要:

    阐述了振冲转换法的加固机理,目的在于将其应用于矿山尾矿库坝的加固。采用振冲置换法对某矿山尾矿库坝进行了现场加固试验,检测测试结果表明加固效果显著。尾矿库坝坡加固后坝体密实度和抗液化能力明显提高。可满足抗液化要求。有关试验成果在随后进行的大面积加固中得到成功应用。试验和实践为振冲置换法在类似尾矿库加固中的推广应用提供了成功经验。

    Abstract:

    The mechanism of vibration and substitution method is presented so as to apply it into reinforcement of the tailings dam. With it field experiment of reinforcement of the taillngs dam in a certain mine was conducted. The experimental results indicate that the effect of reinforcement is notable, the density of the tailings dame is improved and the anti - liquefaction ability is enhanced, which can meet the requirement of anti - liquefaction. The relevant experimental achievements are applied in the following large - scale reinforcement successfully. The experiments and practices offer some successful experiences for the popularized application of vibration and substitution method in the reinforcement of similar tailings dames.

    参考文献
    相似文献
    引证文献
引用本文

曾芳金 蔡关峰.振冲置换法加固尾矿库坝的机理和应用[J].矿业研究与开发,2005,(6):83-85

复制
分享
文章指标
  • 点击次数:
  • 下载次数:
  • HTML阅读次数:
  • 引用次数:
历史
  • 收稿日期:2005-01-27
  • 最后修改日期:
  • 录用日期:
  • 在线发布日期:
  • 出版日期: