分条式上向进路块石混凝土胶结充填采矿法的应用
DOI:
作者:
作者单位:

作者简介:

通讯作者:

中图分类号:

TD853.34

基金项目:


Application of Vertical Slice and Upward drift mining with Rock cemented Filling
Author:
Affiliation:

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
  • |
  • 文章评论
    摘要:

    在会东铅锌矿二期扩建工程投产前,露天开采的矿石品位低,于是在井下开采中应用分条式上向进路充填采矿法先采出部分富矿,以满足冶炼厂对原料的要求,同时,也可对矿山还贷和提高经济效益起到一定的作用。作者对此采矿方法在会东矿的应用作了较详细的介绍。

    Abstract:

    Before the commissioning of the 2nd phase expansion project at Huidong lead Zinc Mine,the grade of ore from opencast mining was lower,Consequently,the vertical slice and upward drift mining with rock cemented filling was applied to underground mining to extract partial rich ore beforehand so as to meet the requirement of raw materials of metallurgical plant and play a role in repaying loans and enhancing economic benefit of the mine as well.The author gave detailed introduction to the application of this mining method in Huidong mine

    参考文献
    相似文献
    引证文献
引用本文

段恒建.分条式上向进路块石混凝土胶结充填采矿法的应用[J].矿业研究与开发,1999,(Z2):

复制
分享
文章指标
  • 点击次数:
  • 下载次数:
  • HTML阅读次数:
  • 引用次数:
历史
  • 收稿日期:
  • 最后修改日期:
  • 录用日期:
  • 在线发布日期:
  • 出版日期: