    摘要:

    铜坑矿填方法改用块石胶结充填后需要使用处于地陷区的溜井,给放块石哑了卡井,跑溜子,电振台振结底泥浆排走困难,漏斗装置大修困难,作者根据其实际经验就解决这些问题进行了有效的探讨,并提出了解决问题的独特见解。

    Abstract:

    As the cemented filling with rod milling tailings has been changed into one with waste rock and mortar in Tongkeng tin mine,the orepass situated in the subsidence area must be used.In this case,the problems on orepass blockage,debris flow out of orepass,slime depositing and hardening under the electric vibrating platform,repair of cone installation and so on are unfavourable to the waste rock filling.According to his experience in practice,the author makes and approach to these problems,and puts forward some special viewpoints on solving them.

    参考文献
    相似文献
    引证文献
引用本文

李雁翎.高大溜井的生产管理[J].矿业研究与开发,1998,(6):11-13