下向分层碎石胶结充填采矿法在前河金矿的应用
DOI:
作者:
作者单位:

作者简介:

通讯作者:

中图分类号:

TD863

基金项目:


AN APPLICATION OF DESENDING CUT-AND-FILL WITH CEMENTED FILLING OF CRUSHED ROCK IN QIANHE GOLD MINE
Author:
Affiliation:

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
  • |
  • 文章评论
    摘要:

    在这一采矿方法的研究和实践过程中,结合矿山实际情况,从理论分析和室内试验入手,采用进路分层充填结构、黄泥接顶、承载层不设吊筋和锚杆、溜矿井用密集木框支护、无掏糟爆破等项新技术和新工艺,降低了水泥和钢材消耗,简化了工艺流程,改善了充填接顶和爆破效果,提高了生产能力。该采矿方法已在生产中推广应用。

    Abstract:

    Combined with the mine reality closely , to start with the theoretical analvsisand the laboratory experiment , in the process of resrarch and practice in this miningmethod,the new technology such access slicing structure ,roof contacted with loess,loadedlayers without cables and rock bolts ,ore passes with close timber square seta,and no-cuthole blasting etc. was used to reduce the consumption of cement and steel,simplify thetechnological process, improve the effectiveness of both roof contacted with filling andbladting, and increase the production capacity. This mining method has been deployed inthe mines.

    参考文献
    相似文献
    引证文献
引用本文

肖有鼎 王元亮.下向分层碎石胶结充填采矿法在前河金矿的应用[J].矿业研究与开发,1994,(4):7-13

复制
分享
文章指标
  • 点击次数:
  • 下载次数:
  • HTML阅读次数:
  • 引用次数:
历史
  • 收稿日期:
  • 最后修改日期:
  • 录用日期:
  • 在线发布日期:
  • 出版日期: