THE DEMONSTRATION OF RATIONAL PRODUCTION CAPACITY IN BAIYIN DEEP LEVEL COPPER MINE
Author:
Affiliation:

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
  • |
  • 文章评论
    摘要:

    白银铜矿自投产以来尚未达到原设计100万t的生产能力。文中对影响达产的诸因素进行了分析,指出年产100万t矿石在技术上受到限制,在经济上也不合理。同时,通过中段矿块生产能力计算和作生产能力平衡图等,认为该矿以年产矿石75万t为宜;并用经济合理的服务年限、合理的中段下降速度和新中段的准备进行了验证,提出该矿必须进行适度的技术改造,才能保证在服务年限内稳产75万t/年。

    Abstract:

    In Baiyin Copper mine one million tons of original design annual capacity has not yet been achieved ever since it was put into production. All factors which cause the failure were analyzed, leading to the conclusion that one million tons capacity is limited technically and unreasonable economically. In the meantime, production capacity of level ore block and capacity balance diagrams indicated that a capacity of 0.75 million tons is rational and this conclution was verified through economically rational service life, rational downward mining rate and development of new level. It was proposed that in the mine some technical modifications cvere needed in order to ensure a stable annual production capacity of 0.75 million tons ore in the service life.

    参考文献
    相似文献
    引证文献
引用本文

宋喜栋.白银深部铜矿合理生产能力的论证[J].矿业研究与开发,1993,(3):20-26

复制
分享
文章指标
  • 点击次数:
  • 下载次数:
  • HTML阅读次数:
  • 引用次数:
历史
  • 收稿日期:
  • 最后修改日期:
  • 录用日期:
  • 在线发布日期:
  • 出版日期: