坑探工程对上部重叠矿床扰动的安全性分析
DOI:
CSTR:
作者:
作者单位:

作者简介:

通讯作者:

中图分类号:

TD325

基金项目:

中南财经政法大学振兴工程科研基金资助项目(90507030113)


Safety Analysis on the Disturbance of Prospecting Tunnel on the Upper Overlapping Deposit
Author:
Affiliation:

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
  • |
  • 文章评论
    摘要:

    罗群岩煤矿与苏家坪铁矿的矿体重叠,上下仅相距60m左右。两矿同时开展探矿工作或有潜在的安全影响。分析计算了苏家坪铁矿探矿的顶板冒落高度、岩层破裂高度与岩层变形下沉高度。分析表明,即使在苏家坪铁矿探矿巷道垮塌的极端情况下,也不会对上部煤矿勘查活动构成安全威胁,进而提出了两矿可同时实施其探矿工作的结论。

    Abstract:

    Sujiaping iron ore body is under Luoqunyan coal body.The distance form the top of fomer to the bottom of of the latter is only 60m meters apart.In this paper,the heights of roof caving of tunnels,and broking and subsidence of rock strata in Sujiaping iron mine after excavation are analyxed and calculated.The results show that even if it is collapse that all of the prospeting tunnels of Sujiaping iron mine in extreme cases,the safety of the upper prospecting work of Luoqunyan coal mine is not threatened.The paper draws a conclusion that the mineral prospecting work of Sujiaping iron mine can be carried out with the Luoqunyan coal mine in the same time.

    参考文献
    相似文献
    引证文献
引用本文

黄志伟,宋君.坑探工程对上部重叠矿床扰动的安全性分析[J].矿业研究与开发,2010,(4):63-65,73