Abstract:The diversion tunnel of a certain hydroelectric power station has been excavated by way of pilot heading combined with smooth blasting, therefore the results were achieved that the unevenness of the excavated surface is less than 10 cm and the overbreak or underbreak of the tunnel is less than 15 cm. This paper describes the determination of smooth blasting parameters, adopted blast-hole layout and cut-hole pattern as well as the construction control.