An Analysis on and the Renovation Project of the Sand Feeding System for the Filling Plant in Wushan Copper Mine
Author:
Affiliation:

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
  • |
  • 文章评论
    摘要:

    因设计考虑欠充分,武山铜矿北矿带原充填站给砂系统故障频繁,严重影响了生产。对给砂系统的故障原因进行了较详细的分析,在此基础上,提出了采用胶带运输机给砂系统的改造方案。改造后,取得了较好的效果,满足了生产的需要。

    Abstract:

    Due to the lack of full consideration in the planning,the trouble with the sand feeding system for the filling plant originally designed for the northern ore belt in Wushan Copper Mine occurred frequently and had serious influence on mining production.An analysis in more detail of the trouble with the sand feeding system was made.Based on this analysis,the renovation project on the employment of belt conveyor sand feeding system was proposed.Through the technical reform of sand feeding system,a better result has been obtained and the requirement of mining production has been satisfied.

    参考文献
    相似文献
    引证文献
引用本文

杨仁兵.武山铜矿充填站给砂系统问题分析及改造方案[J].矿业研究与开发,1998,(5):14-16

复制
分享
相关视频

文章指标
  • 点击次数:
  • 下载次数:
  • HTML阅读次数:
  • 引用次数:
历史
  • 收稿日期:
  • 最后修改日期:
  • 录用日期:
  • 在线发布日期:
  • 出版日期:
文章二维码

《矿业研究与开发》严正声明

关闭